Roadworks to Clarendon Way

Building Number(s): N/A
Building Name(s): N/A
Date: 28 July 2025 12:00 AM to 31 October 2025 11:30 PM

Is this work scheduled or planned? Yes
Type of work: Development/building work –
Type of disruption: Roadworks –

Background information:

As part of the Steam Main improvement work we will be introducing road traffic management to Clarendon Way highway to facilitate the construction of a new condensate management facility.  The construction works will take approx. 3 months from commencement. It is anticipated that there will be some traffic congestion on Clarendon Way during the period of this notice.  A Pedestrian way will be maintained as part of the traffic management plan.

Reason for works/service interruption: The Steam improvement works are essential to ensure continuity of heating, hot water and steam utilising processes at the University. 

For more information, contact Bob Douglass at
Telephone No: 07957 227094
 Email: r.douglass@leeds.ac.uk